Project plan

Project phase Task Schedule
Phase one . September-May 2001
Pilot studies Evaluation of prototype
Technology
End of August 2001
Project partner seminar Project initiationBriefing regarding project objective and content August 2001
Development Product development on the basis of pilot studies and continuous user tests March 2002

Project partner seminar Briefing regarding development concept, integration of modules in web pages and model for user testing. End of March 2002
Implementation and user tests 1st implementation and wind up of user tests.First part of the programme at AUB, HBÅ, KB, and RUB. April 2002
Phase two . May - February 2003
Further development and continuous user tests. Incorporation of user test results from the first part of the programme and continuous user test results in the further development. September 2002
Project partner seminar Briefing regarding the integration of modules in homepages and model for user testing. End of September 2002
Implementation and user test Implementation of the second part of the programme and user test of selected modules at AUB, HBÅ, KB and RUB. October 2002
Evaluation Evaluation of the SWIM modules October - December 2002
Conclusion Reporting, publication of results via conference. February 2003